  • August
  • September
  • October
  • November
  • December
  • January
    • Shutdown Sensing board was not grounded properly
      • lots of funky problems until that was resolved 
    • Adi did not review each board as thoroughly as he should have. DRC. Gerber Viewer. Design Spreadsheet.
      • Never again...
  • February 
    • PCBway was shutdown for 4 weeks!! Fuck!
      • Lead times grew from 24hrs to 12-20 days! Fuck!
    • OSHpark is super expensive! and slow! Fuck!
      • QC issues with their prototype PCB as well! 
    • Discharge should have been on the High Side AIR Mount board
      • Calls for respin of high side and low side air mount boards
    • Last minute sensing enclosures call for major redesign for entire subteam
      • may lead to problems with project ownership
    • Shipped wrong gerbers for LV interface
      • fixable with rework, but not ideal
    • Lost a set of very specific resistors for Suspension Strain board
      • Set populating and testing back for over a week
    • ATmega 16M1 to 328p SPI fix leads to issues with flashing code 
      • not a major issue but inconvenient
    • IMD Latch had a wrong footprint assigned for an op amp.
      • Error in op amp circuit
      • Calls for respin
    • Received 20 pages of feedback for the FMEA.
      • Lots of work to be done to get that submitted on time. 
  • March